Current Schedule of Works
M42 Junction 5a Works
All main work activities associated with the construction of junction 5a on the
M42 (approximately 1.8km south of the existing junction 6) are scheduled
between February 2021 and August 2023.
New Link Road Works
All main work activities associated with the new link road that will run between
junction 5a on the M42 and Clock Interchange are scheduled between February
2021 and May 2024, however September 2023 is when the link road and new
junction is scheduled to open to traffic.
The attached provides a high-level summary of the various construction works
required to deliver the link road and the dates these aspects of work are schedule
to take place:  please click here.